Working Overnights: How YVR Got a New Runway While Keeping Flights on Time

Just after nightfall, once the final aircraft had departed, Vancouver International Airport’s (YVR) North Runway shifted into a different kind of operation. Lights came on, equipment was stationed, and construction teams moved into position. For the next eight hours, Amrize teams would work across one of Canada’s busiest runways—with the understanding that by sunrise, they’d have it ready for commercial traffic once again.

 

Initially constructed in the 1990s, the North Runway was in need of an upgrade. As a critical part of YVR’s airfield network that handles hundreds of aircraft movements each day, the work was carefully planned to take place during six months of overnight shifts starting at 10 p.m. By sunrise every day, crews returned the runway to service with its surface, line painting and lights ready to safely accommodate the day’s flights schedule. This overnight window would shape every aspect of the project.

Planning for success: The daily routine that kept nightly paving on schedule

Each evening before the shift began, teams reviewed minute-by-minute schedules, examined weather conditions, and coordinated assets for the night shift. Since all work had to be completed, inspected, cleaned up and handed back to airport operations before the first morning arrival, planning and communication were just as crucial as the paving itself.

“Amrize deployed dedicated, highly trained crews to deliver a complex paving program under a tight scheduling window. The Mitchell Island team ensured the 400-tonne-per-hour plant maximized uptime and produced consistent, high-quality asphalt mix. Pave teams mastered the use of dual 10-meter screeds paving in echelon with mm GPS control—an approach that minimized cold joints, improved ride quality, and elevated productivity.”

Brice Babuik

Pave Manager, Greater Vancouver Area, Amrize

The right mix: Specialized asphalt and paving techniques make for fast work

Runways must withstand heavy planes and near-constant traffic. Working in partnership with Kiewit, YVR’s General Contractor, Amrize supplied and placed approximately 154,000 metric tonnes of advanced asphalt solutions across the entire North Runway and its connecting taxiways

 

The asphalt mix incorporated additives and fibers to make it stronger and longer-lasting. It was also produced with Environmental Product Declarations (EPDs), which provide transparent information about the environmental impact of the materials.

Well-oiled machines: Technology delivers consistency night after night

 

With 100 crew members operating 100 pieces of equipment across the full project night after night, consistency was critical. For Amrize’s portion, that meant managing up to 60 milling and paving units, supported by 30 trucks and transfers to keep material moving efficiently. Technology lent a hand. To ensure repeatable results over the program, while maximizing efficiency, quality and speed. Amrize used advanced systems, including: 

 

  • mmGPS Paver Control: Automated screed adjustments for consistent surfaces
  • Thermal Imaging: Real-time monitoring of asphalt temperature for optimal compaction
  • Wide Screeds: Fewer joints, greater efficiency, higher nightly volumes

 

Together, these tools helped Amrize lay 220 millimeter-depth overlays in 120-meter increments—ultimately providing a smooth, uniform surface across the 65-meter-wide, three-kilometer-long runway and its 11 taxiways. 

Team dynamics: Partnership delivers on-schedule results  

The North Runway Program shows the power of a close partnership between YVR, Kiewit, Amrize, and the broader construction and operations teams. Through extensive pre-planning, high-performance materials, and specialized equipment, the project stayed on schedule throughout the six months of construction, which concluded in Fall 2025.

The approach—nightly work, innovative materials, precise execution and seamless handovers—is now drawing interest from airports across North America looking to modernize major airfield infrastructure while keeping flights on schedule, passengers on the go and airlines doing business.

"Amrize is proud to have successfully delivered critical infrastructure to YVR alongside our construction partners, meeting exacting standards for strength and durability, without disrupting daily operations. By combining years of experience, advanced technology and months of careful planning, the team hit every milestone for this generational project. The result is a runway that not only supports safe and efficient operations today, but will serve the airport and the community for decades to come." 

Gord Bird

General Manager, Greater Vancouver Area, Amrize